SHERIDAN COLLEGE
School of Applied Computing and Engineering Sciences
ARCHITECTURAL  TECHNOLOGY
ARCH 21158 ARCHITECTURAL DETAILING 2: Commercial

 


MODULE # 03: Barrier-Free Ramp Design


Learning Outcomes

"By the end of the module, Learners will be able to:  


Contents


1.  The Process of Creating the Construction Details

Given the requirements of the OBC as compiled in the last class (OBC data matrix)

Given the ramp configuration as determined in your design showing the desired direction of approach and ramp location

Given the change of elevation, required slope and maximum landing spacing allowed, calculate the overall length of your ramp

Research the assigned assembly components, limitations and opportunities, advantages and disadvantages

Begin by drawing the the section reference locations on your sketch plan.

Identify special situations where the typical detail needs to be modified.

Determine all the required components and attachments.


2.  Type 1: Wood

 essentially designed to resemble a sloping wood deck 

 

  ELEMENT DESCRIPTION
  Running Surface 38 x 140 PTP decking perpendicular to direction of travel with 10mm spacing between boards
Handrail / Guardrail 38 x 140 PTP 
Structure 38 x 235 PTP stringers with 38 x 89 ledgers and cross bracing
Foundations / Footings 90 x 90 wd posts @ 3000 O.C. max on 150mm Dia. poured concrete piers to 1200 below grade minimum

 

 

 

 

 

 

 

 

 

 

 

special areas of concern are:


3.  Type 2: Poured Concrete 

essentially designed to resemble a poured concrete sloped slab on beams or as a slab on grade with retaining walls.

 

  ELEMENT DESCRIPTION
Running Surface 100mm slab on grade c/w a broom finish
Handrail / Guardrail 38mm Dia. steel pipe
Structure 200mm poured concrete walls
Foundations / Footings 200mm poured concrete foundation walls on 400 x 200mm dp strip footings

 

 

 

 

 

 

 

 

 

 

 

 

special areas of concern are:


4.  Type 3: Pre-cast Concrete Units:  

essentially designed to resemble a unitized retaining wall with sloping walkway made from interlocking pavers.

 

  ELEMENT DESCRIPTION
 

Running Surface

interlocking precast concrete pavers (ie Unilock or equal)

Handrail / Guardrail

38mm Dia. steel pipe

Structure

segmented precast concrete unit retaining wall (ie Stackstone, Pisa II or equal)

Foundations / Footings

granular base and backfill per manufacturer's directions

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

special areas of concern are:

Further References:

 Risi Stone of Thornhill Ontario web site (www.risistone.com

Unilock (www.unilock.com)

 

  5.  Type 4: Hybrid System:  

Combination of poured concrete and steel construction essentially designed to resemble a poured concrete floor on steel decking

 

Below:  University of Toronto at Mississauga South Building Entrance ramp ELEMENT DESCRIPTION

Running Surface

 75mm (3") concrete slab on steel decking (depth depends on span)

Handrail / Guardrail

38mm Dia. steel pipe

Structure

 HSS posts on concrete piers with steel channel stringers 






 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.  Guard and Handrail Assemblies

 

 

 

To compare the properties and advantages and disadvantages of each of the four assembly types visit the  comparison chart

 

Go to Assignment 1 from the Course Contents page


Back to Top