
| SHERIDAN COLLEGE |
| School of Applied Computing and Engineering Sciences |
| ARCHITECTURAL TECHNOLOGY |
| ARCH 21158 ARCHITECTURAL DETAILING 2: Commercial |
MODULE # 03: Barrier-Free Ramp Design
Learning Outcomes
"By the end of the module, Learners will be able to:
Contents
1. The Process of Creating the Construction Details
Given the requirements of the OBC as compiled in the last class (OBC data matrix)
Given the ramp configuration as determined in your design showing the desired direction of approach and ramp location
Given the change of elevation, required slope and maximum landing spacing allowed, calculate the overall length of your ramp
Research the assigned assembly components, limitations and opportunities, advantages and disadvantages
Begin by drawing the the section reference locations on your sketch plan.
Identify special situations where the typical detail needs to be modified.
Determine all the required components and attachments.
essentially designed to resemble a sloping wood deck
| ELEMENT | DESCRIPTION | |
|
Running Surface | 38 x 140 PTP decking perpendicular to direction of travel with 10mm spacing between boards |
| Handrail / Guardrail | 38 x 140 PTP | |
| Structure | 38 x 235 PTP stringers with 38 x 89 ledgers and cross bracing | |
| Foundations / Footings | 90 x 90 wd posts @ 3000 O.C. max on 150mm Dia. poured concrete piers to 1200 below grade minimum |
special areas of concern are:
the transition from the grade to the 38 x 140 wood running surface of the ramp
recommended post spacing
intermediate guardrail support
closing of the space underneath the ramp
essentially designed to resemble a poured concrete sloped slab on beams or as a slab on grade with retaining walls.
| ELEMENT | DESCRIPTION | |
|
|
Running Surface | 100mm slab on grade c/w a broom finish |
| Handrail / Guardrail | 38mm Dia. steel pipe | |
| Structure | 200mm poured concrete walls | |
| Foundations / Footings | 200mm poured concrete foundation walls on 400 x 200mm dp strip footings |
special areas of concern are:
handrail and guardrail support
closing of the space underneath the ramp if poured retaining walls not present
4. Type 3: Pre-cast Concrete Units:
essentially designed to resemble a unitized retaining wall with sloping walkway made from interlocking pavers.
| ELEMENT | DESCRIPTION | |
|
Running Surface |
interlocking precast concrete pavers (ie Unilock or equal) |
|
Handrail / Guardrail |
38mm Dia. steel pipe |
|
|
Structure |
segmented precast concrete unit retaining wall (ie Stackstone, Pisa II or equal) |
|
|
Foundations / Footings |
granular base and backfill per manufacturer's directions |
special areas of concern are:
unsupported wall height maximums
special footing conditions
running surface construction for interlocking pre-cast pavers
handrail and guardrail support
Further References:
Risi Stone of Thornhill Ontario web site (www.risistone.com)
Unilock (www.unilock.com)
5.
Type
4:
Hybrid System:
Combination of poured concrete and steel
construction
essentially
designed to resemble a poured concrete floor on
steel decking Running
Surface 75mm
(3") concrete slab on steel decking (depth depends on span) Handrail /
Guardrail 38mm Dia.
steel pipe Structure HSS
posts on concrete piers with steel channel stringers
Below: University
of Toronto at Mississauga South Building Entrance ramp
ELEMENT
DESCRIPTION

![]() |
![]() |
|
|
|
![]() |
![]() |
|
|
|
To compare the properties and advantages and disadvantages of each of the four assembly types visit the comparison chart
Go to Assignment 1 from the Course Contents page